Monday, 23 May 2016

Paving of the northern terrace will continue, with works anticipated to be completed next week. Refurbishment of the ground-floor is ongoing with flooring starting Monday, fit-out of bathrooms underway, painting commencing in the toilets and infill glazing to continue. The paving on the east side of the building is complete, and the north-east stairwell is again available for emergency egress.

The closure of the Reid Library and the modifications to the electrical supply that occurred on Saturday 14 May were successfully completed on time.

Works planned to occur: 23 May – 3 June (2 week look ahead)

Activities occurring:

  • Paving to the northern terrace
  • Glazing panel infill install to the north and south
  • Ongoing services installation
  • Painting continuing
  • Installation of fins continuing
  • Ongoing general refurbishment works ground-floor
  • Air-heating shutdown to the whole building anticipated to occur over a 2 to 3 day period


What to expect/how this may impact you
Saw cutting and compacting noise on the northern terrace due to the installation of the pavers.

There will be an air-heating shutdown to the entire building while the heating pump is replaced and plinths are poured.
The shutdown is anticipated to last for a 2 to 3 day period, and expected to be undertaken within the next fortnight - actual dates will be confirmed prior to the air-heating shutdown.

Intermittent noise due to drilling and floor stripping.

What you need to do
No unauthorised access is allowed at all times. Visitors should register with the site office and contact the site manager before entering, and are required to be escorted unless a valid induction with Western Projects has been completed.

Project enquiries
If you have any questions relating to this project, please contact the Project Manager, Marijke Schlingmann, NS Projects on 0438 067 445.