Tuesday, 27 October 2015
  • Site preparation commencing Tuesday 27 October, basement car park
  • Noisiest works scheduled to take place out of hours
  • Timeframe of works: October to early 2016

Updated: Friday 30 October

Upcoming weekend works for lift installation
Please be aware that from Saturday 31 October until mid-January, the following weekend works will be works occurring in the car park basement including concrete drilling (there will be a level of noise vibration and dust associated with these works).

This work has been scheduled out of hours to minimise the impact on building occupants.


Works on the much anticipated new lift at 55 Broadway are scheduled to commence early this week.

Installation of the new lift will link the basement car park through to level 2, to ensure the building meets building codes, and improve access into the building.

Access to the car park, building and upper car park levels will not be affected while works are underway.

The lift is scheduled to be fully operational in early 2016.

Please note: where ever possible high disruption works will take place outside of normal business.

If you have any questions relating to these works please contact Mark Croager, Project Officer on 6488 1339 or [email protected]