Monday, 29 June 2015
  • Essential electrical upgrade to ALVA building from Tuesday 30 June to Monday 13 July.
  • The power outage will affect the west side of all floors
  • Staff offices, studios and computer laboratories will have restricted access during the scheduled shutdown.
  • The shutdown will not affect security access to the building.

    Please be aware that works to replace electrical boards in the ALVA building will commence on Tuesday 30 June, until Monday 13 July. This is an important electrical upgrade and part of the University’s Life Cycle Replacement program.

    Campus Management has worked with Faculty of Architecture, Landscape and Visual Arts in determining the schedule and timing of the work.

    Access to the ALVA building will be restricted during this upgrade. The power outage will affect the west side of all floors, with each floor being shut-down for a two day period. Please see the schedule of works below.

    FLOOR DATE
    Fourth floor 30 June to 1 July
    Third floor 2 to 3 July
    Second floor 6 to 7 July
    First floor 8 to 9 July
    Ground floor 10 to 13 July

    Please note : Staff offices, studios and computer laboratories will have restricted access during the scheduled shutdown. The shutdown will not affect security access to the building.

    If you have any questions or queries, please contact Campus Management on 6488 2034.